Records request of August 31, 2026 · working-group memo · September 28, 2026 · updated October 2, 2026

BVSD was asked how High Peaks came to move. It sent the bond office's files.

Six days after BVSD proposed moving High Peaks into the Douglass building, a Boulder resident asked for every record of how the move was considered. On September 12 the district produced 78 files. None is about the move. They are the repair history of the building High Peaks shares with BCSIS and the bond office's working forecasts, and the forecasts show when construction was stopped at the schools in the proposal, and what had been spent on them by then.

Working-group copy. Not linked from the site and set not to be indexed; share this address only within the group. Everything below is linked to a primary source; open it before quoting it. No covering letter came with the files, so this memo says what they contain, not what BVSD searched or withheld. It reaches no legal conclusion.
  1. No record in the production is about moving High Peaks. The request asked for correspondence on relocating the school “to any other physical campus”, for site-visit records and calendar invitations, and for proposals or feedback from the school's staff and PTO. The 78 files hold none of it. Douglass is named in the request itself, in a list of buildings in a 2019 maintenance plan, in rows of the bond ledgers, and in committee minutes that record a pancake breakfast. No email is to or from a Board member, the senior planner or a PTO address. request all 78 files
  2. Records about the move existed, and BVSD produced them to another requester. The district's files for a different request were made on Friday, September 11, the afternoon before the 78. Among them are twelve emails about the move from August 19 to 25, 2026, each inside this request's dates and its first item and each carrying its search words. None is among the 78. Seven are to or from the High Peaks principal, a custodian the request names by role, among them his letter to families on the evening of August 25: “If approved in September, the plan would be for High Peaks Elementary School to be relocated to the site of Douglass Elementary School.” No covering letter or privilege log came with the 78 to say whether they were found. the twelve Aug 25 letter
  3. One email is about the process. On January 30, 2026 the BCSIS principal told the school's staff that the two principals at Aurora 7 had met Dr. Rob Anderson and Dr. Laura De La Cruz the afternoon before: “They are meeting with all elementary principals as part of the engagement process to address declining enrollment trends.” The email passes on three points, ending “Our school is seen and valued.” The deck attached is the one shown to the Board on January 27, and its list of options includes “Relocate focus programs”. Jan 30 email
  4. The bond director's mailbox is in this production. The production made for Boulder Reporting Lab searched four mailboxes, and the bond director's was not among them. Kris Stoppenhagen, executive director of bond planning and construction, is on 24 of the 54 emails here. With them came seven editions of the 2022 bond expenditure forecast, December 2024 to August 18, 2026, each carrying the ledger behind it. the earlier production
  5. The first hold is dated March 3, 2026. Against Creekside and against the Mapleton early childhood center the forecast carries one note: “03.03.26 Working meeting with KS --> Project on Hold for BOE declining enrollment assessment”. Neither is named in the August 25 proposal. Both are in the last group of universal-access playgrounds, with Bear Creek, Heatherwood and Mesa. The ledger shows first payments on all five playgrounds in February, $389,111 in all, and every one of them back at zero by July 31 with the contracts still open at $2,167,207. The workbooks do not say why. March 10 edition ledger lines
  6. On March 10 construction came out of the forecast at twelve schools. They are Birch and every elementary school in the bond's last phase outside the mountains: Bear Creek, Coal Creek, Community Montessori, Eisenhower, Eldorado, Flatirons, Foothill, Heatherwood, Kohl, Mesa and Superior. Flatirons went from $567,000 in 2026-27 and $998,400 in 2027-28 to $55,000 and nothing, with $1,493,380 left unassigned. By April 22 each balance had been parked in April to June 2028. Nederland's two projects kept their dates. The August 25 proposal closes, moves, reconfigures or sends students to all twelve. every edition, every row
  7. Work on the High Peaks building was stopped between March 10 and April 22. The Board approved a $1,123,323 construction contract for the building on November 18, 2025, on consent, 7 to 0, with work to start May 26, 2026. On March 6 the abatement consultant sent a draft bid manual with proposals due March 31. The March 10 forecast still has the work in July to December 2026. The April 22 forecast has it a year later. On May 26 the bond office reported in public that “BCSIS/High Peaks work” had been “put on hold pending BOE declining enrollment decisions”. The proposal to move High Peaks out of the building and Community Montessori into it was presented on August 25. bid manual May 26 report
  8. Birch was under construction that summer. Its commitments rose from $226,976 to $1,167,984 during February 2026, $943,227 of that a construction contract. By July 31, $442,507 had been paid on the contract. The August 18 forecast puts the remaining $723,588 in July to December 2027, after the school's last year under the proposal. At Flatirons, Mesa and Community Montessori the architects were paid through the summer: $67,835, $32,175 and $72,660 by July 31. August 18 edition
  9. The ledger gives the pieces of the district's “about 3 million”. On September 15 the chief financial officer put the offset from “not investing in the closed schools” at “about 3 million”. On July 31 Birch, Flatirons and Mesa had $4,432,115 of 2022 bond budget between them. $828,525 had been paid and $1,915,025 was under contract, which leaves $3,603,590 unspent and $2,517,090 uncommitted. Community Montessori's building, which also closes, had a further $2,463,279 unspent. Nothing in the production shows which of these the district counted. Sept 15, 2:51:48
  10. The 2014 bond put $48.5 million into the four schools the proposal closes. Douglass, rebuilt, had $24,242,269. Mesa had $9,279,920, Birch $8,315,937 and Flatirons $6,635,623. Community Montessori's building, which the proposal also closes, had $8,021,325, and the BCSIS and High Peaks building $7,944,032. The figures are the district's own project-to-date report. 2014 bond report
  11. The building Community Montessori would share has an open roof claim, and a heating fault that was still being fixed in 2025. In May 2024 a consulting engineer wrote that in part of the building there was “no chance in meeting the space temperature requirements probably anytime the outside air temperature is below 35F”; the change order for the controls of new duct heaters is dated September 24, 2025. Of the roof put on in 2017 a project manager wrote in August 2024 that the contractor “walked away from the project so we are light on the closeout documents”; the assistant superintendent sent the architect's agreement to outside counsel in August 2025; the May 26 report says the roof is “to be replaced under a manufacturer's warranty claim”. The state's assessors put the building's needs at $8,335,705 against a replacement value of $25,695,478, and Heatherwood's, where part of Douglass would go, at $11,102,719 against $26,121,926. engineer Heatherwood report
  12. The accountability committee's minutes record how closure was described in February. On February 3, 2026, by the minutes, the committee heard that principals and teachers were being asked to “Force rank for their school: grade reconfiguration, consolidation, closure”, that “Closing schools and redistributing, that's the quickest”, and that “When we close/consolidate, we will have empty buildings.” One member asked: “Why are we moving when schools are at the yellow stage?” On March 3, told that Birch had written its own survey, the superintendent's minuted answer is “Don't do it, BVSD is”. Feb 3 minutes Mar 3 minutes
  13. The production reads as a keyword return. Fifty-three of the 55 emails contain the words High Peaks, in the message or in an attachment. The other two carried a workbook that is missing from the folder, and the next copy of it does. Nine of the 54 the district produced are dated before January 1, 2025, where the request begins. The matches include eight emails arranging classroom observations of a math curriculum, a manifest for pumping a grease trap, and a roofing manufacturer's inspection from 2018. Forty-nine of the PDFs were made in one nine-minute run on Saturday, September 12. Six are marked redacted, and what is blacked out in them is plans of the building; the same plans are left visible in four files, one of them among the six.
  14. What the records do not show. Who decided to move High Peaks, when, or on what analysis. Whether anyone from the district or the school visited Douglass or Heatherwood. What BVSD searched, what it withheld and why. The production is silent on all of it, and a production assembled this way is weak evidence that no such record exists. What it does establish is the order of events in the bond office: a hold in March, the High Peaks building stopped by April, and a proposal in August that touches every school whose construction had been taken out of the forecast.

The request

It went by email to cora@bvsd.org and communications@bvsd.org on Monday, August 31, 2026 at 10:40 a.m., six days after the proposal was presented. It covers January 1, 2025 to August 31, 2026.

ItemWhat it asks forWhat the production holds
1“All emails, text messages, Google Chat records, memos, meeting notes, and written correspondence referencing the potential relocation, movement, or facility transfer of High Peaks Focus School / High Peaks Elementary to any other physical campus”, Heatherwood and Douglass includedNothing
2“All records, electronic mail, calendar invitations, attendance logs, site-visit feedback forms, post-visit debrief summaries, or presentation slides concerning any physical site visits or facility walkthroughs” by High Peaks staff, PTO officers, parents or district officials at Heatherwood, Douglass “or alternative receiving sites”Nothing. The visits in the files are a state assessor's survey of the BCSIS and High Peaks building, a roofing manufacturer's inspection of it in 2018, and classroom observations of a math curriculum. There is no calendar invitation
3“Any formal proposals, survey results, feedback submissions, letter campaigns, position papers, or data models” from High Peaks staff, PTO officers or committees to Board members or administrators “regarding building preferences, facility suitability, or relocation conditions”Nothing
4From any PTO account on a district server, communications that mention Douglass, Heatherwood, relocation, moving, consolidation, receiving school, site visit, building swap or facilityNothing from a PTO account
5Correspondence between PTO officers' outside addresses and any administrator, Board director or planner containing those termsNothing

The request · target custodians and keywords · as sent

“Search Keywords: High Peaks AND (Heatherwood OR Douglass OR relocation OR site visit OR facility swap OR building transfer OR debrief OR walkthrough).”

The custodians it names are the superintendent, Assistant Superintendent Rob Price, the senior planner, the director of facilities, the members of the Board, the High Peaks principal and administration, and the school's PTO officers and SAC and DAC representatives.

The request also asks for an itemized cost estimate before any fee is incurred, for a fee waiver, and, where anything is withheld, for “a written privilege log citing the specific legal authority for each redaction”.

The folder holds 78 files: 55 emails turned into PDF, one of them the request itself, and 23 attachments, 16 of them Excel workbooks. It holds no letter from the district, no cost estimate and no log. The files cannot show whether any was sent.

What the 78 files are

SubjectFilesWhat they areThe words that match
The request1The requester's own email, converted with the restAll of them
The process8The BCSIS principal's note to staff with the January 27 Board deck. A welcome to a new District Accountability Committee representative with the committee's agendas and minutes for January, February and March 2026Heatherwood, in the deck and in the minutes; Douglass, in the minutes
The bond office27Thirteen emails among the bond accountant, the bond director and the finance office, and fourteen workbooks: seven editions of the 2022 bond forecast, the project dashboard, year-end commitments, and the closing accounts of the 2014 bondEvery school is a row
The Aurora 7 building29The building BCSIS and High Peaks share: its heating, its roof, the state's condition report, the construction contract for summer 2026, asbestos abatement and air quality. The state's report on Heatherwood came with them“Site visit”, in a roof inspection and an engineer's proposal; “relocation”, of utilities, in the contract conditions; “walk-through”, for bidders
Other subjects13Eight emails arranging classroom observations of a math curriculum; a recess programme; the manifest for pumping a grease trap; the school's newsletter; the board packet of the district's foundation; a 2019 maintenance plan sent to another district as an example“Site visits” and “debrief”, for the observations; Heatherwood, as a pickup point for day camps; “potential office relocation”, in the foundation's budget

The forecast, edition by edition

The 2022 bond expenditure forecast is one workbook, kept by the bond accountant and corrected by the bond director. Each row is a school, each column a quarter, and a notes column records what was settled at their working meetings. The figures below are dollars still to be spent, by fiscal year. Unassigned is budget the edition had not yet placed in any quarter. A shaded cell is where a school's construction was taken out or moved.

Kris Stoppenhagen to Janey Bowen · Tuesday, March 10, 2026, 4:18 p.m. · email · workbook

“Also, this copy overrides the one you sent after our meeting as there were a handful of projects that were still showing old projections.”

SchoolMarch 3March 10April 22August 18
Set for summer 2026
BCSIS and High PeaksHigh Peaks leaves; Community Montessori arrives2026-27460,261
2027-280
unassigned608,159
2026-271,068,420
2027-280
2026-270
2027-281,065,963
2026-2717,142
2027-281,290,531
BirchCloses2026-27653,807
2027-280
unassigned200,946
2026-2755,000
2027-280
unassigned799,753
2026-2755,000
2027-28794,448
2026-2753,639
2027-28723,588
WhittierTakes part of Flatirons2026-27729,141
2027-280
unassigned218,445
2026-27947,586
2027-280
2026-27932,697
2027-280
2026-27896,090
2027-280
Crest ViewNot in the proposal2026-27595,839
2027-280
unassigned1,005,626
2026-271,501,465
2027-280
2026-271,508,035
2027-280
2026-271,328,644
2027-280
CreeksideNot in the proposal2026-270
2027-280
unassigned349,792
2026-270
2027-280
unassigned329,792
noteon hold
2026-270
2027-28347,456
noteon hold
2026-270
2027-28425,808
noteon hold
MapletonNot in the proposal2026-27135,000
2027-280
unassigned215,856
2026-27135,000
2027-280
unassigned215,856
noteon hold
2026-27197,507
2027-28215,856
noteon hold
2026-27241,326
2027-28215,856
noteon hold
Set for summer 2027
FlatironsCloses2026-27567,000
2027-28998,400
2026-2755,000
2027-280
unassigned1,493,380
2026-2755,000
2027-281,507,666
2026-2739,166
2027-281,502,314
MesaCloses2026-27337,000
2027-28552,766
unassigned323,160
2026-2724,000
2027-280
unassigned1,188,925
2026-2724,000
2027-281,194,515
2026-2721,149
2027-281,285,709
Community MontessoriBuilding closes; school moves2026-27911,000
2027-281,562,949
2026-2755,000
2027-280
unassigned2,399,872
2026-2755,000
2027-282,416,520
2026-2755,000
2027-282,408,279
Bear CreekTakes Mesa2026-27839,000
2027-281,465,793
unassigned29,152
2026-2755,000
2027-280
unassigned2,278,945
2026-2755,000
2027-282,313,361
2026-2736,340
2027-282,318,105
Coal CreekTakes part of Douglass2026-27663,000
2027-281,429,696
2026-2765,000
2027-280
unassigned1,742,223
2026-2765,000
2027-281,770,223
2026-2770,340
2027-281,713,544
EisenhowerTakes part of Douglass2026-271,016,000
2027-281,936,345
2026-2770,000
2027-280
unassigned2,881,271
2026-2770,000
2027-282,924,271
2026-2761,289
2027-282,889,333
HeatherwoodTakes part of Douglass2026-271,188,000
2027-282,038,880
unassigned615,979
2026-2795,000
2027-280
unassigned3,769,859
2026-2795,000
2027-283,808,229
2026-2795,000
2027-283,928,612
FoothillTakes part of Flatirons2026-27959,000
2027-282,179,565
2026-27100,000
2027-280
unassigned2,986,198
2026-27100,000
2027-283,013,326
2026-2798,706
2027-282,941,499
KohlTakes Birch2026-271,221,000
2027-282,404,090
2026-27100,000
2027-280
unassigned3,523,906
2026-27100,000
2027-283,575,906
2026-27100,000
2027-283,494,231
SuperiorTakes part of Monarch2026-27205,000
2027-28319,822
2026-2730,000
2027-280
unassigned488,873
2026-2730,000
2027-28496,325
2026-2730,000
2027-28490,611
EldoradoBecomes K-52026-271,318,673
2027-28519,422
2026-270
2027-280
unassigned1,556,515
2026-270
2027-281,708,794
2026-270
2027-281,732,068
Nederland ElementaryNot in the proposal2026-27458,000
2027-28775,112
2026-27390,000
2027-28840,487
2026-27390,000
2027-28818,090
2026-27375,210
2027-28801,739
Nederland Middle-SeniorNot in the proposal2026-273,760,000
2027-286,200,437
2026-272,760,000
2027-286,130,761
2026-272,903,836
2027-286,130,761
2026-272,796,924
2027-286,225,316

Four things changed between the March 3 and March 10 editions.

By April 22 two more things had changed. The unassigned balances at the twelve schools had been placed in the last quarter of 2027-28, April to June 2028. And the BCSIS and High Peaks work had moved from July to December 2026 to July to December 2027. The workbook gives no reason for either.

The August 18 edition is the bond director's “reconciled expenditure forecast”, sent a week before the proposal was presented. It carries the same notes and the same marks. Aug 18 email

What BVSD had said in public

The hold was not hidden. Four public statements bear on it.

What the production adds is the date, the list and the money. The hold entered the bond office's books on March 3, six weeks before the first regional engagement session on April 13 and twelve weeks before it was reported to the Board. It reached the building High Peaks is in by April 22. And the ledger shows what each school had received by then.

What the schools in the proposal had received

Two of the district's own reports are in the production: every 2014 bond project's spending to date, run on June 30, 2025, and the 2022 bond ledger as of July 31, 2026, inside the August 18 workbook. Under contract includes what has been paid. The forecast columns are the August 18 edition's. 2014 bond 2022 bond ledger, every edition

School2014 bond, spent2022 bond, budgetUnder contractPaidForecast
Closed, moved or reconfigured
DouglassCloses; High Peaks moves in24,242,26967,00367,00367,0032026-270
2027-280
BirchCloses8,315,9371,425,9581,218,694670,7062026-2753,639
2027-28723,588
FlatironsCloses6,635,6231,621,400180,34079,9202026-2739,166
2027-281,502,314
MesaCloses9,279,9201,384,757515,99177,8982026-2721,149
2027-281,285,709
Community MontessoriBuilding closes; school moves8,021,3252,569,000209,483105,7212026-2755,000
2027-282,408,279
BCSIS and High PeaksHigh Peaks leaves; Community Montessori arrives7,944,0321,647,0621,458,880341,3952026-2717,142
2027-281,290,531
MonarchBecomes a middle school9,205,5083,878,0873,599,9173,435,4922026-27464,068
2027-280
EldoradoBecomes K-510,705,4073,624,8172,052,6661,892,7482026-270
2027-281,732,068
Taking their students
KohlTakes Birch8,042,5034,286,306832,691692,0742026-27100,000
2027-283,494,231
Bear CreekTakes Mesa9,239,5412,787,641865,053433,1952026-2736,340
2027-282,318,105
FoothillTakes part of Flatirons9,353,7074,063,8081,441,5971,027,1702026-2798,706
2027-282,941,499
WhittierTakes part of Flatirons8,209,1061,466,9511,185,680590,4672026-27896,090
2027-280
Coal CreekTakes part of Douglass6,622,5262,257,784576,085473,9002026-2770,340
2027-281,713,544
EisenhowerTakes part of Douglass7,050,3653,731,399881,545780,7762026-2761,289
2027-282,889,333
HeatherwoodTakes part of Douglass7,023,7384,096,614951,14373,0022026-2795,000
2027-283,928,612
FiresideTakes part of Monarch9,215,6392,214,2242,083,7462,073,4972026-27140,727
2027-280
SuperiorTakes part of Monarch7,565,842575,00090,54054,3892026-2730,000
2027-28490,611
Birch, Flatirons and Mesa24,231,4804,432,1151,915,025828,5252026-27113,954
2027-283,511,612
With Community MontessoriThe four buildings that close32,252,8057,001,1152,124,508934,2462026-27168,954
2027-285,919,891

Three things stand out.

The playgrounds

The last five universal-access playgrounds were to be built in summer 2026. The ledger shows a site-work contract at each by January and a first payment at each in February. By July 31 every payment is gone from both the project ledger and the general ledger, and the contracts remain.

SchoolSite-work contractPaid by Feb 28, 2026Paid by July 31, 2026In the forecast
Heatherwood724,671137,2950Marked (UA)
Creekside413,40580,0740Marked (UA); on hold, March 3
Mesa406,37098,8400Marked (UA)
Bear Creek379,17720,5020Marked (UA)
Mapleton243,58452,4000On hold, March 3
Five playgrounds2,167,207389,1110

The building High Peaks would leave

BCSIS and High Peaks share the Aurora 7 campus at 3995 Aurora Avenue, which staff call A7. Under the proposal High Peaks goes to Douglass and Community Montessori takes its place. Twenty-nine of the files are this building's paperwork.

Heatherwood

The only other state report in the production is Heatherwood's, of November 5, 2025. It gives a building of 60,797 square feet from 1971, a replacement value of $26,121,926 and needs of $11,102,719, an index of 0.43. Heating and ventilation score 0.83, with $4,193,481 of needs against a system worth $5,042,380, and electrical 0.72. The 2022 bond budgets $4,096,614 for the school. On September 15 Rob Price said the district could “accommodate some of the special education modifications within the phase 4 work that's already planned out there”. The same emails show the state had also reported on Birch, Flatirons and Community Montessori in 2025; those reports were not produced. report 2:59:44

What the accountability committee was told

The District Accountability Committee is required by state law, and each school sends it a representative. On March 25, 2026 the superintendent's office sent a new representative the last three agendas and sets of minutes, copied to the BCSIS principal, and that email is in the production. The minutes are notes taken by committee members, not a transcript.

January 6, 2026 · minutes

The Mesa representative: “What has been decided on any school being consolidated? Which schools have been chosen?” The minuted response: “Nothing has been decided. Lots of rumors, but look back at what BVSD has done to be proactive. We will be presenting on 1/27.”

February 3, 2026 · Rob Price and Dr. Anderson presenting · minutes

“No decisions have been made.”

Engagement will not: “Guarantee preservation of specific schools”, “Delay action”, “Transfer decision-making authority away from the Board of Education”.

Under “Reflections from Dr. Anderson”: “Crest View, Eisenhower, Mesa so far”; “Force rank for their school: grade reconfiguration, consolidation, closure”; “our Board has said no to doing nothing”.

Asked whether every change would come in 2027-28: “Closing schools and redistributing, that's the quickest — either because one school has room, or b/c schools split into lower elementary and upper elementary”.

Asked about leasing buildings: “When we close/consolidate, we will have empty buildings. JeffCo closed 16 schools; sold zero schools. We will have to solve for this in the implementation phase. If we were to sell a property, it has to be rezoned.”

From the floor: “we're yellow, we have time. Why are we moving when schools are at the yellow stage?”

March 3, 2026 · minutes

From the school reports: “Birch Elem has created a survey and would like to make sure it's not duplicated with BVSD efforts”. The minuted response: “Response (Anderson): Don't do it, BVSD is”.

From the Board's report, given by Alex Medler: “Engagement process is best way to get feedback to board and district, not parallel engagement practices.”

February 3 is a month before the bond office's first hold. The yellow stage in the question from the floor is the committee framework's Enrollment Advisory phase. The thresholds memo

How the production was put together

What the files showDetail
One exportForty-nine of the 62 PDFs were made by the district's email converter, wkhtmltopdf 0.12.6, and every one is stamped Saturday, September 12, 2026, between 10:44:47 and 10:53:49 a.m. The request itself is one of them, at 10:45:25
Matches on wordsFifty-three of the 55 emails contain “High Peaks” in the message or an attachment. Forty-one also contain one of the request's other terms. Most of the rest are about the school's building
Outside the dates asked forNine emails are from March to December 2024. The request begins on January 1, 2025
Who is in itThe bond director is on 24 emails, three project managers on ten or eleven each, the bond accountant on ten. Rob Price is on three. The superintendent is on one, as a director of the district's foundation. No Board member, and not the senior planner
Missing attachmentsTwo emails of August 18, 2026 name a workbook, “2022 Bond Expenditure Forecast AUG26 -UPDATED FY'26 (JB).xlsx”, that is not in the folder. The reply of that afternoon carries the next copy
RedactionSix PDFs are named “Redacted” and carry no metadata. What is blacked out is plans of the building: a floor plan inside an engineer's proposal, and two roof sheets. No text is blacked out and no page cites an exemption. The floor plan is visible on page 8 of one of the six, and the two roof sheets are visible in three other files
No covering letterNo response from the district, cost estimate or list of what was withheld is among the files

The copies on this page

Seventy of the 78 files are served as they were received. Five are served as copies with something blacked out, and three are held back. The files as received are in the working group's document store, and the inventory gives the SHA-256 of each.

What another request returned

Another requester asked BVSD for records on Douglass and High Peaks from January 1, 2025 to August 25, 2026, inside the dates this request covers. The district produced 35 files. Twenty-six of their 34 PDFs carry the stamp of the same email converter as the 78, every one on Friday, September 11, 2026, between 4:07 and 4:12 p.m., the afternoon before the 78 were made; the other eight are marked redacted and carry none. None of the 35 is among the 78.

Asked for on August 31Held by BVSD, and produced to another requester
Records“All emails, text messages, Google Chat records, memos, meeting notes, and written correspondence referencing the potential relocation” of High Peaks “to any other physical campus”, Douglass includedTwelve emails about the move: the principal's letter to families, the district's letter to the school, four replies to the principal, and the communications office's preparations with the network directors and the Douglass principal
DatesJanuary 1, 2025 to August 31, 2026August 19 to 25, 2026
CustodiansBoard members, “district administrators”, and High Peaks and PTO representatives; among the custodians listed by name or role, “High Peaks Principal/Administration”Seven to or from the High Peaks principal. Five among the chief communications officer, the assistant superintendent of schools, the three network directors and the Douglass principal
Search wordsHigh Peaks with Heatherwood, Douglass, relocation, site visit, facility swap, building transfer, debrief or walkthroughEvery one has High Peaks with Douglass, Heatherwood or relocation
Held back“a written privilege log citing the specific legal authority for each redaction”None of the twelve is among the 78. No covering letter or log came with the 78
SentFrom and toWhat it says
To or from the High Peaks principal · 7
Aug 25, 11:28 a.m.Matt Jenkins, communications manager, to Christopher Basten, High Peaks principalWritten “after this morning’s meeting”. He is the communications liaison “for the schools involved in the High Peaks / Community Montessori / BCSIS Branch”, and the principal’s folder holds a sample letter “specific to your situation: closure, relocation, reconfiguration, etc.” email
Aug 25, 6:24 p.m.The district to High Peaks families and staff; the principal’s copy“The proposal recommends relocating High Peaks Elementary to the current Douglass Elementary building”. Under “How we arrived at this proposal”: “High Peaks is BVSD’s most in-demand focus school. Positioning the building at the Douglass campus, which is located between two major east/west arterial roads will give more students, particularly those in east county, access to the school.” email
Aug 25, 8:00 p.m.Christopher Basten to High Peaks families“If approved in September, the plan would be for High Peaks Elementary School to be relocated to the site of Douglass Elementary School.” letter
Aug 25, 8:15–9:02 p.m.Four people who received the letter, to the principalThanks and good wishes, each reply quoting the letter in full 8:15 8:45 8:59 9:02
Among the communications office, the network directors and the Douglass principal · 5
Aug 19, 5:00 p.m.Randy Barber, chief communications officer, to the three network executive directors; copied to Neil Anderson, assistant superintendent of schoolsFor “tomorrow, when you start meeting with impacted principals”: the order of announcements on August 25, a folder for each school with its letter, a sample letter, talking points and a one-sheet, and a communications coordinator for each branch, one of them “Relocate High Peaks, Relocate Community Montessori (Southwest) & (Northwest - Douglass)” email
Aug 20, 2:00 p.m.Randy Barber to Jonathan Wolfer, Douglass principal, through Google DriveAn invitation to contribute to a shared folder named “Close Douglass, Relocate High Peaks, Relocate Community Montessori, Receiving Schools: Coal Creek, Eisenhower, Heatherwood, BCSIS (co-locate)” notice
Aug 20–21Randy Barber, Neil Anderson and the three network directors“I hope the meetings with the impacted principals went well today.” The school letters, filed by branch under “Relocate High Peaks, Relocate Community Montessori, Co-Locate BCSIS” and five others, are reviewed that night and the next morning, for translation at noon on August 21 Aug 20, 7:13 p.m. 7:51 p.m. Aug 21, 6:45 a.m.

Six more files in that production, all of August 25, refer to the move: the district's letter to all families and staff, which lists “Move High Peaks Elementary to the former Douglass Elementary campus”; its letters to the Douglass and Community Montessori communities; the liaison's note to the Community Montessori principal and her reply; and the chief communications officer's note that night to the district leadership list. all families Douglass Community Montessori liaison reply leadership list

The 78 files do include emails addressed to the High Peaks principal, on a recess programme in January 2025 and on classroom observations in February 2026. Neither production holds a calendar invitation of any kind. The production made for Boulder Reporting Lab, whose request asked for calendar invitations too, holds none either. that production

Whether the search for this request found the twelve and left them out, or never reached them, the files cannot show. The privilege log the request asked for, or BVSD's account of the search it ran, would.

What cuts the other way

What would settle it

Timeline

Documents

The production

DateFrom and toWhat it isFile
The request · 1
Aug 31, 2026The requester to cora@bvsd.org and communications@bvsd.orgThe requestCOLORADO_OPEN_RECORDS_ACT_CORA_REQUEST_C_R_S_24_72_201_ET_SEQ_HIGH_PEAKS_RELOCATION_HEATHERWOOD_AND_DOUGLASS_ELEMENTARY_COMMUNICATIONS.pdf contact details blacked out
2 pages · 73 KB
The process · 8
Jan 30, 2026Jennifer Barr, BCSIS principal, to BCSIS staffThe two principals’ meeting with the superintendent on January 29; the January 27 Board deck attachedUpdate_from_principal_meeting.pdf
18 pages · 3.5 MB
Mar 25, 2026Laura Shafer, executive secretary to the superintendent and Board, to a new committee representative and the two co-chairs; copied to the BCSIS principalWelcome to the District Accountability Committee, with the last three meetings’ papersWelcome_to_the_District_Accountability_Committee.pdf
1 page · 53 KB
AttachmentCommittee agenda, January 6, 2026DAC Meeting Agenda (January 6, 2026).pdf
1 page · 296 KB
AttachmentCommittee minutes, January 6, 2026DAC Meeting Minutes (January 6, 2026).pdf
8 pages · 262 KB
AttachmentCommittee agenda, February 3, 2026DAC Meeting Agenda (February 3, 2026).pdf
2 pages · 297 KB
AttachmentCommittee minutes, February 3, 2026DAC Meeting Minutes (February 3, 2026).pdf
12 pages · 701 KB
AttachmentCommittee agenda, March 3, 2026DAC Meeting Agenda (March 3, 2026).pdf
1 page · 296 KB
AttachmentCommittee minutes, March 3, 202620260303 DAC Minutes.pdf
5 pages · 199 KB
The bond office · 27
Mar 27, 2024David Clabaugh, project accountant, to Kris Stoppenhagen and Charles ZachemskyBalances left on 2014 bond projectsSome_recent_2014_Bond_Project_Balance_Info_may_be_helpful_.pdf
1 page · 46 KB
AttachmentCost view of every bond project as of March 26, 2024, the 2014 projects included2014 BOND PROJECT CLOSEOUT Update-- Cost View 03.26.2024.xlsx
29 KB
Dec 12, 2024David Clabaugh to Kris StoppenhagenThe forecast worksheet handed over as the accountant leftBond_Total_Expenditure_Forecast_Worksheet_12_3_24_Copy.pdf
1 page · 45 KB
Attachment2022 bond expenditure forecast, December 2024 edition2022 Bond Expenditure Forecast 12.2024 REVISED BUDGET.xlsx
942 KB
Feb 24, 2025Thomas Blahak, project manager, to an architecture firm“Looks like the only remaining jobs are Phase 4”Upcoming_Projects.pdf
1 page · 62 KB
AttachmentThe 2022 bond project dashboard: every project by phase, manager, architect and contractorCopy of 2022 Bond Project Dashboard .xlsx
125 KB
June 30, 2025Janey Bowen, bond accountant, to a finance colleague; the chief financial officer is in the threadReports for the bond draw scheduleRe_Bond_redemption_account.pdf
1 page · 63 KB
Attachment2014 bond income statement to December 20212014 BOND INCOME STATEMENT Dec.2021 Final.xlsx
2.0 MB
AttachmentEvery 2014 bond project’s spending to date, run June 30, 2025eBuilder 2014 Project Detail Expense Report.xlsx
271 KB
Oct 22, 2025Janey Bowen to Sarah ShermanYear-end construction commitments, for checkingReview.pdf
1 page · 47 KB
AttachmentConstruction commitments at June 30, 2025FY25 - Construction Commitments Note - at 06.30.25 - NEW.xlsx
503 KB
AttachmentOpen purchase orders, and a log of bond items taken to the Board since 2016FY25 - Construction Commitments Notes New 07.01.25.xlsx
333 KB
Feb 18, 2026Janey Bowen to Kris Stoppenhagen“Please see the attached updated reports”Requested_Reports.pdf
1 page · 48 KB
AttachmentInterest earnings forecast, January 20262022 Bond - Interest Earnings Forecast JAN26.xlsx
2.4 MB
Attachment2022 bond expenditure forecast, January 2026 edition2022 Bond Expenditure Forecast 01.2026 MAY-REVISED FY_26.xlsx
1.0 MB
Feb 20, 2026Janey Bowen to Kris StoppenhagenThe forecast with actuals updated; differences to be assigned to quartersUpdated_Expenditure_Forecast.pdf
1 page · 50 KB
Attachment2022 bond expenditure forecast, February 2026 edition2022 Bond Expenditure Forecast 02.2026 MAY25-UPDATED FY_26.xlsx
1.2 MB
Mar 3, 2026Janey Bowen to Kris Stoppenhagen“Updated with February totals for us to work with this afternoon”updated_forecast.pdf
1 page · 48 KB
Attachment2022 bond expenditure forecast as it went into the March 3 working meeting2022 Bond Expenditure Forecast 03.2026 MAY25-UPDATED FY_26.xlsx
1.1 MB
Mar 10, 2026Kris Stoppenhagen to Janey BowenThe bond director’s revised copy, which “overrides the one you sent after our meeting”Re_Expenditure_forecast_revised.pdf
1 page · 90 KB
Attachment2022 bond expenditure forecast, March 10, 2026 revision2022 Bond Expenditure Forecast 03.10.2026 MAY25-UPDATED FY_26 (1)_KDS (1).xlsx
1.1 MB
Apr 22, 2026Kris Stoppenhagen to Janey BowenThe updated sheet, for the oversight committee’s chartRe_Expenditure_forecast.pdf
1 page · 90 KB
Attachment2022 bond expenditure forecast, April 22, 2026 edition2022 Bond Expenditure Forecast 04.22.2026 -UPDATED FY_26 KDS.xlsx
1.1 MB
Aug 18, 2026Janey Bowen to Kris StoppenhagenThe worksheet with 2026 and 2027 actuals. The workbook it carried is not in the folderUpdated_with_actuals.pdf
1 page · 48 KB
Aug 18, 2026Janey Bowen to Kris StoppenhagenThe same workbook again. It is not in the folderupdated_worksheet.pdf
1 page · 47 KB
Aug 18, 2026Kris Stoppenhagen to Janey BowenThe reconciled forecast, a week before the proposalRe_bond_admin_scenarios.pdf
1 page · 91 KB
Attachment2022 bond expenditure forecast, August 18, 2026 edition, ledger to July 312022 Bond Expenditure Forecast AUG26 -UPDATED FY_26 (JB) (2)_KS.xlsx
1.2 MB
The Aurora 7 building · 29
June 6, 2024A consulting engineer to the HVAC manager and a project managerThe heating in the 2018 addition; design proposal for electric duct heatersRE_BVSD_BCSIS_High_Peaks_Redacted.pdf
9 pages · 447 KB
June 11, 2024e-Builder notification to Stephen HenryThe change order, as loggedFYI_22_BCSIS_High_Peaks_Elementary_22_BCSIS_High_Peaks_Elementary_CO_06_11_2024_Redacted.pdf
6 pages · 306 KB
June 11, 2024Stephen Henry, bond project manager, to the engineerChange order for the heating designBCSIS_High_Peaks_Design_services_Redacted.pdf
6 pages · 284 KB
June 11, 2024The engineer to Stephen HenryReply on the change orderRE_BCSIS_High_Peaks_Design_services_Redacted.pdf
6 pages · 307 KB
June 12, 2024e-Builder notification to Derrell WaltonThe change order, as logged the next dayFYI_22_BCSIS_High_Peaks_Elementary_22_BCSIS_High_Peaks_Elementary_CO_06_12_2024_Redacted.pdf floor plan blacked out
11 pages · 527 KB
July 17, 2024Gene Temanson, project manager, to the building maintenance manager and Stephen HenryRoof damage by door 15, and whether the manufacturer’s warranty covers itRe_BCSIS_adjacent_to_door_15.pdf two roof sheets blacked out
56 pages · 19.8 MB
Aug 13, 2024Gene Temanson to a roofing consultantWhat the district holds on the 2017 roofRe_BCSIS_Roof_Warranty.pdf two roof sheets blacked out
55 pages · 16.6 MB
Feb 5, 2025The roofing consultant to Charles Zachemsky, project managerWhat was never finished on the roof; the roof and the 2026 designRe_BCSIS_HP_Redacted.pdf
56 pages · 21.0 MB
Mar 14, 2025Charles Zachemsky to Kris StoppenhagenCloseout papers found in e-Builder: “It seems we have an executed warranty though”Re_BCSIS_Roof.pdf two roof sheets blacked out
64 pages · 17.3 MB
Mar 25, 2025A state facility assessor to Kris Stoppenhagen and the building’s facilities contactScheduling the state’s condition survey of the building, April 2 to 4, 2025RE_BVSD_High_Peaks_BCSIS_A7_4_2_4_4_2025.pdf
1 page · 102 KB
Mar 25, 2025The facilities contact to the assessor“I have you on the calendar”Re_BVSD_High_Peaks_BCSIS_A7_4_2_4_4_2025_03252025_1219PM.pdf
1 page · 113 KB
Mar 25, 2025Kris Stoppenhagen to the facilities contactAsks that the two principals be toldRe_BVSD_High_Peaks_BCSIS_A7_4_2_4_4_2025 (2).pdf
2 pages · 159 KB
Apr 22, 2025Colorado Department of Education, Capital Construction, to Kris Stoppenhagen and Charles ZachemskyThe state’s facility report on the BCSIS and High Peaks buildingFacility_Insight_School_Report_Boulder_Valley_Re_2_BCSIS_High_Peaks_ES.pdf
107 pages · 1.9 MB
AttachmentThe same report as a separate file250422-BCSIS_High_Peaks_ES.pdf
102 pages · 1.8 MB
AttachmentThe report’s system-by-system table250422-BCSIS_High_Peaks_ES_Systems.xlsx
33 KB
May 30, 2025Charles Zachemsky to Kris Stoppenhagen, forwarding the contractorEarly procurement exhibits for Platt and for BCSIS and High PeaksFwd_Platt_MS_and_BCSIS_High_Peaks_ES_Early_Procurement_Amendment_Documentation.pdf
136 pages · 2.6 MB
Aug 26, 2025Rob Price, assistant superintendent, to the district’s outside counselThe 2016 architect agreement, sent “for this matter”BCSIS_Roof_Issue.pdf
30 pages · 581 KB
Sept 5, 2025Dillon Recen, assistant director of facilities, to two project managersA controls contractor’s proposal for the duct heatersFwd_BVSD_High_Peaks_HVAC_Improvements_Scope.pdf
5 pages · 266 KB
Sept 5, 2025Gene Temanson to Dillon RecenReply on the proposalRe_BVSD_High_Peaks_HVAC_Improvements_Scope (2).pdf
6 pages · 275 KB
Sept 5, 2025Gene Temanson to Kris StoppenhagenThe proposal, forwardedFwd_BVSD_High_Peaks_HVAC_Improvements_Scope_09052025_0447PM.pdf
6 pages · 277 KB
Sept 23, 2025The controls contractor to Dillon RecenRevised, lower proposalRE_BVSD_High_Peaks_HVAC_Improvements_Scope.pdf
5 pages · 270 KB
Sept 24, 2025Gene Temanson to two project managers and Dillon RecenThe revised proposal, forwardedFwd_BVSD_High_Peaks_HVAC_Improvements_Scope_09242025_1048AM.pdf
7 pages · 300 KB
Sept 24, 2025The controls contractor to Gene TemansonChange order for the heating coil controlsRE_BCSIS_HP_Heating_Coil_Project_CO.pdf
8 pages · 375 KB
Nov 4, 2025Stephen Henry to the contractorNotes on the guaranteed maximum price exhibitsRe_GMP_Exhibits_Platt_BCSIS_High_Peaks_Manhattan.pdf
74 pages · 1.1 MB
Nov 5, 2025Colorado Department of Education, Capital Construction, to Kris Stoppenhagen and Charles ZachemskyThe state’s facility report on HeatherwoodFacility_Insight_School_Report_Boulder_Valley_Re_2_Heatherwood_ES.pdf
108 pages · 2.0 MB
AttachmentThe report’s system-by-system table251105-Heatherwood_ES_Systems.xlsx
33 KB
Nov 7, 2025Stephen Henry to the contractorFinal exhibits for three projects before they “put those in for the board”Re_Revised_High_Peaks_Document.pdf
221 pages · 4.5 MB
Mar 6, 2026The owner’s representative for abatement to Stephen Henry and Kris StoppenhagenDraft asbestos abatement manual and bid dates for the summer 2026 workBCSIS_Abatement_Project_Manual.pdf
114 pages · 1.4 MB
June 15, 2026Carey Jensen, director of facilities, to Rob PriceAnswer to a voicemail from the BCSIS principal: two 2018 air-quality reviews, and an offer to commission a full building assessmentRe_New_Voicemail_From_5506_In_Mailbox_6425.pdf
44 pages · 2.3 MB
Keyword matches on other subjects · 13
Jan 9, 2025The bullying prevention specialist to the High Peaks principalA recess training programmePlayworks_follow_up.pdf
1 page · 124 KB
Sept 25, 2025High Peaks to its familiesThe school’s weekly newsletterHigh_Peaks_Newsletter_Week_of_September_29_2025.pdf held: photographs of students
5 pages · 4.4 MB
Dec 30, 2025Rob Price to an administrator in another districtBVSD’s 2019 draft facility maintenance plan, sent as an exampleFacility_Roadmap.pdf held: photographs of students
97 pages · 20.1 MB
Jan 23, 2026Impact on Education to its directors, the superintendent among themThe foundation’s January 29, 2026 board packetJanuary_Board_packet.pdf held: personal addresses
26 pages · 1.3 MB
Feb 9, 2026A network administrator to five principalsClassroom observations of the new math curriculum, called site visits in the email, each with a debriefSW_Network_Internal_Math_Visits.pdf
1 page · 35 KB
Feb 9, 2026The administrator to a principalThe same threadRe_SW_Network_Internal_Math_Visits_02092026_0448PM.pdf
2 pages · 45 KB
Feb 9, 2026A principal to the administratorThe same threadRe_SW_Network_Internal_Math_Visits.pdf
1 page · 41 KB
Feb 9, 2026A principal to the administratorThe same threadRe_SW_Network_Internal_Math_Visits_02092026_1019PM.pdf
2 pages · 45 KB
Feb 10, 2026A principal to the administratorThe same threadRe_SW_Network_Internal_Math_Visits_02102026_0826AM.pdf
1 page · 35 KB
Feb 10, 2026A principal to two staff membersThe same threadFwd_SW_Network_Internal_Math_Visits.pdf
2 pages · 63 KB
Feb 11, 2026A principal to a teacherThe same threadRe_SW_Network_Internal_Math_Visits_02112026_0316PM.pdf
2 pages · 96 KB
Feb 26, 2026The administrator to the High Peaks principalThe same threadRe_SW_Network_Internal_Math_Visits_02262026_0220PM.pdf
2 pages · 38 KB
June 24, 2026A waste hauler’s system to a district employeeManifest for pumping the kitchen grease trapJob_36982993_BVSD_BCSIS_High_Peaks_Elem_has_been_approved.pdf
4 pages · 401 KB

From the other production

DateFrom and toWhat it isFile
To or from the High Peaks principal · 7
Aug 25, 2026Matt Jenkins, communications manager, to Christopher Basten, High Peaks principalHis introduction as communications liaison for the High Peaks, Community Montessori and BCSIS branchCommunications_Liaison_Intro_Redacted.pdf
1 page · 53 KB
Aug 25, 2026The district to High Peaks families and staff; the principal’s copyThe proposal and High Peaks, 6:24 p.m.BVSD_Resilient_Schools_Proposal_and_High_Peaks_Elementary.pdf
2 pages · 206 KB
Aug 25, 2026Christopher Basten to High Peaks families“High Peaks Principal letter - School Relocating”, 8:00 p.m.High_Peaks_Principal_letter_School_Relocating.pdf
1 page · 145 KB
Aug 25, 2026A recipient of the letter, to the principalReply, 8:15 p.m.Re_High_Peaks_Principal_letter_School_Relocating_08252026_0915PM_Redacted.pdf
1 page · 145 KB
Aug 25, 2026A recipient of the letter, to the principalReply, 8:45 p.m.Re_High_Peaks_Principal_letter_School_Relocating_08252026_0945PM_Redacted.pdf
2 pages · 156 KB
Aug 25, 2026A recipient of the letter, to the principalReply, 8:59 p.m.Re_High_Peaks_Principal_letter_School_Relocating_08252026_0959PM_Redacted.pdf
1 page · 140 KB
Aug 25, 2026A recipient of the letter, to the principalReply, 9:02 p.m.Re_High_Peaks_Principal_letter_School_Relocating_Redacted.pdf
1 page · 144 KB
The communications office, the network directors and the Douglass principal · 5
Aug 19, 2026Randy Barber, chief communications officer, to the three network executive directors; copied to Neil Anderson, assistant superintendent of schoolsCommunications materials for the meetings with the impacted principalsCommunications_materials_for_tomorrow_s_meetings_Redacted.pdf
2 pages · 99 KB
Aug 20, 2026Randy Barber to Jonathan Wolfer, Douglass principal, through Google DriveThe shared folder for the Douglass, High Peaks and Community Montessori branchFolder_shared_with_you_Close_Douglass_Relocate_High_Peaks_Relocate_Community_Montessori_Receiving_Schools_Coal_Creek_Eisenhower_Heatherwood_BCSIS_co_locate_.pdf
1 page · 40 KB
Aug 20, 2026Randy Barber to Neil Anderson and the three network directorsThe school letters, for review before translationPlease_take_a_look_at_the_school_letters_for_your_impacted_schools.pdf
2 pages · 70 KB
Aug 20, 2026Brooke Daerr, Southwest network director, to Tamara Acevedo, Northwest network director; copied to the othersReply on the Southwest lettersRe_Please_take_a_look_at_the_school_letters_for_your_impacted_schools_08202026_0851PM.pdf
2 pages · 97 KB
Aug 21, 2026Randy Barber to Daniel Ryan, East network director; copied to the othersThe thread to its endRe_Please_take_a_look_at_the_school_letters_for_your_impacted_schools.pdf
3 pages · 349 KB
The announcement to other schools and to the district’s leaders · 6
Aug 25, 2026Matt Jenkins to Natalie Celeste, Community Montessori principalThe same introduction as communications liaisonCommunications_Liaison_Intro_08252026_1229PM_Redacted.pdf
1 page · 53 KB
Aug 25, 2026Natalie Celeste to Matt JenkinsReplyRe_Communications_Liaison_Intro_Redacted.pdf
1 page · 73 KB
Aug 25, 2026The district to all families and staff; a network director’s copyThe proposal, 6:13 p.m.Resilient_Schools_Proposal.pdf
4 pages · 692 KB
Aug 25, 2026The district to Douglass families and staff; the principal’s copyThe proposal and Douglass, 6:16 p.m.BVSD_Resilient_Schools_Proposal_and_Douglass_Elementary.pdf
2 pages · 240 KB
Aug 25, 2026The district to Community Montessori families and staff; the principal’s copyThe proposal and Community Montessori, 6:23 p.m.BVSD_Resilient_Schools_Proposal_and_Community_Montessori.pdf
2 pages · 195 KB
Aug 25, 2026Randy Barber to the district leadership listResources for leaders, with a one-sheet for each branch_bvs_dlt_Re_Resilient_Schools_Resources.pdf
2 pages · 87 KB

Worked from the production

production-inventory.csv, the 78 files with dates, senders and checksums · bond-forecast-by-edition.csv, every row of the seven editions by quarter · bond-ledger-by-edition.csv, budget, commitments and payments for every project at each ledger date · bond-ledger-accounts-selected-schools.csv, the same by account for the schools in the proposal.

On the district's systems

Reports of the bond office to the Board: October 28, 2025 · February 2026 · May 26, 2026.

The BCSIS and High Peaks contract: first amendment, on the agenda of November 18, 2025 as item 8.6.

Meetings in the working group's transcripts: October 21, 2025 · November 18, 2025 · January 27, 2026 · August 25, 2026 · August 31, 2026 · September 15, 2026 · September 22, 2026.

All records pages